IT Project Management MScIT 4th Term 2016 Past Paper UOS

University of Sargodha
M. Sc. 4th Term Exam 2016
Subject: I.T
Paper: I.T Project Management (IT-4349)
Time Allowed: 2:30 Hours
Maximum Marks: 80
Objective Part (Compulsory)
Q.1. Write short answers of the following in 2-3 lines each. (16*2)
i. What is cash flow forecasting?
ii. Define version control.
iii. What is Project mitigation?
iv. What is resource scheduling?
v. What is version control?
vi. Define statement of work?
vii. Write name for any two resource scheduling techniques?
viii. How we find the time estimation for project.
ix. What is cash flow forecasting?
x. What is incremental model?
xi. What are stakeholders?
xii. Define activity.
xiii. Write name for any two software process models.
xiv. How we control the quality of project?
xv. What is extreme programming?
xvi. What are software metrics?
Subjective Part (3*16)
Q.2. Draw an activity network using backward pass, for the activities mentioned below. Identify the critical path.
Q.3. How to define project scope. Explain project activities and work breakdown structure.
Q.4. How we can select an appropriate process model. Differentiate b/w V-model and Water Fall model.
Q.5. Explain any two classical mistakes while developing Software projects.
Q.6. What is configuration management? Differentiate between configuration control and version control.